Contract: Supply and place F72 steel reinforcement mesh in concrete leaving space for control/expansion joints...  Reinforcement mesh to be raised on bar chairs throughout.

These are bar chairs for lifting the reinforcement mesh ...

 

 

 

 

... in such a way that it is in the middle of the concrete where it strengthens the concrete rather than flat on the ground.  (THIS PIC FROM THE INTERNET SHOWS HOW IT SHOULD BE DONE)

 

As you can see from these photographs - Mr Murone installed no chairs, just laid the mesh flat on the ground.

Murone Pave-Crete Concrete Melbourne Stockland

Murone Pave-Crete Concrete Melbourne Stockland